Next phase for Kriegers Flak wind farm foundations

 ce93b7c97ea8831859bbe17c36b83648
ce93b7c97ea8831859bbe17c36b83648
Published on

Jan De Nul Group and Smulders have joined forces to build two gigantic gravity-based foundations for the high-voltage station of the Danish offshore wind farm Kriegers Flak.

Luxembourg-based Jan De Nul said the foundations, which have a weight of 10,000 tonnes and 8,000 tonnes, will be constructed on top of a barge in the port of Ostend.

The foundations consist of a concrete part (the so-called gravity based foundations, or GBF) and a steel structure on top of it.

Jan De Nul is responsible for the design and construction of the concrete GBF, while the Belgian-based Smulders is in charge of the design and construction of the steel shafts and decks to be placed on top.

The steel structures were constructed at Hoboken and were shipped to the port of Ostend last weekend.

The steel structure will be placed on top of the concrete structure, after which the foundations will be ready to be transported to Denmark.

Jan De Nul is in charge of the installation of the foundations, the ballasting and the placement of scour protection.

Kriegers Flak, located in the Baltic Sea, will consist out of two parts. The west section, Kriegers Flak A, will have a total capacity of 200MW. The east section will have a total capacity of 400MW.

Each section will dispose of its substation, serving both for the future Krieger Flaks offshore wind farm and as an interconnector between the Danish and German power net.

By 2022, it will start generating electricity for 600,000 households. The interconnector project is funded by the European Energy Program for Recovery.

Related Stories

No stories found.
logo
Baird Maritime / Work Boat World
www.bairdmaritime.com