Van Oord completes T&I work for East Anglia ONE offshore wind farm

 97ccf57b88ba253cc5dc92ad21261841
97ccf57b88ba253cc5dc92ad21261841
Published on

Van Oord has completed work on a transportation and installation (T&I) contract in support the East Anglia ONE offshore wind farm for client ScottishPower Renewables.

As main contractor, Van Oord transported and installed all 102 three-legged jacket foundations for the 714MW wind farm, which is expected to become operational in 2020.

The company said that most of the installations were conducted at depths of more than 40 metres in the North Sea in rough waters and with minimal visibility.